The Cleveland Memorial Bridges Loop would use excess road capacity to create a separated bicycle and pedestrian facility linking the protected bicycle lane and promenade on the Detroit-Superior Bridge with the existing separated multi-use path from Eagle Avenue across the Lorain-Carnegie Bridge.
The Cleveland Memorial Bridges Loop would complete a crucial gap in Cleveland bike and pedestrian network and is the first step in to build a network of stress-free bike/ped accommodations that connect Downtown to the neighborhoods.

Rendering of Memorial Bridges Loop - Full Buildout
For updated information on the Memorial Bridge Loop visit the proejct website.
Project Details/Presentations/Updates:
-
March 2018: Feasibility Study completed by Leadership Cleveland
-
April 2018: Initial stakeholder presentation with Trust for Public Land, Bike Cleveland, and Cleveland City Planning Commission
-
August 2021: City of Cleveland engages consultant to engineer and develop cost estimates
-
March 2022: City of Cleveland begins seeking funding for construction
-
July 2022: Rep. Shontel Brown secures $432,000 in Community Project Funding for construction of the Memorial Bridges Loop
-
January 2024: The City of Cleveland secures full funding for the project through commitments from NOACA and City funds, totaling an additional $1.1M
-
January-October 2025: City and ODOT move forward with design and engineering plans + community engagement
-
June 2026: Construction begins (14 months)